Florida road reconstruction project
The City of Durango residents approved a construction bond in the fall of 2008 to fund the Florida Road Reconstruction project. CEI was awarded a design build contract earlier this year to reconstruct Florida Road from E. 3rd Ave./15th St. northeasterly to East Animas/CR 250. Utility Construction began in late fall of 2009 and will continue through the summer of 2011, weather permitting. Roadway construction will be done in phases.
Traffic wishing to travel outbound (easterly) will be detoured via 32nd Street to East Animas Road. Traffic control measures will be in place to direct traffic through and detour around the construction. Motorists are encouraged to drive at an appropriate speed and obey the traffic signs.
Mueller Engineering, subcontractor for CEI prepared the construction plans for the project. To view the construction plans click here.
Concrete Express Incorporated is currently under contract with the City of Durango to construct the roadway.
When completed, this project will provide safer transportation for cyclists and pedestrians with:
- 5-foot wide concrete bike lanes on both sides of the roadway
- 10-foot wide sidewalk on the north side of the roadway
- signalized pedestrian crossing
The completed project will also make vehicle travel safer with:
- center left turn lanes
- traffic roundabout at the intersection of Riverview Drive
- traffic signal at the intersection of North College Drive
Aesthetic improvements include landscaping trees bordering the roadway, and center landscape islands.
The project is anticipated to be complete the summer of 2011.